The resurgence of Famavi after a year

Process of action of the party affected by the fire

On July 16, 2020 we had a fire at our facility. There were no personal casualties but many materials. Our painting machine suffered most of the damages that could have been caused by the fire. After the rapid execution by firefighters and police was completed, the fire was extinguished very quickly.

 

 

Our only priority was to gradually recover our production and resume it as soon as possible. We created an action plan to start the works as soon as possible and rebuild the painting machine. And so it was, the organization and the guidelines so that each phase of preparation was precise was like climbing stairs.

 

First we removed what was affected by the fire and then we modeled the important parts of the painting machine. Part of degreasing and complete cleaning together with the special treatment to achieve full adherence of the paint.

Later on we carried out the painting section, whose process by electrostatic application of polyester powder paint took a long time since the installation of 20 special guns was not easy. And finally, the drying part was installed, a process to which the product is subjected once the paint has been applied to seal it.

 

THANK YOU!